A baseline schedule accepted without checking becomes the basis of all progress tracking and every claim. Eight simple checks help judge its quality before accepting it.
The eight checks
- Logic: every activity has at least one predecessor and one successor (except start and finish).
- Constraints: imposed dates are rare and justified.
- Lags: no negative lags; positive lags limited and explained.
- Relationship types: most links are finish-to-start.
- Durations: long activities are broken down so they can be tracked.
- Float: very high total float points to missing logic.
- Critical path: continuous from project start to finish.
- Resources and costs: loaded where the contract requires it.
Most of these checks can be automated from a schedule export; the interpretation remains an experienced planner's job.