A constructability review is most useful when it happens early. Before going to tender, ten simple questions catch most of the issues that later turn into delays, variations or rework.
The ten questions
- Is the construction sequence explicit and consistent with site phasing?
- Are access, laydown areas and lifting zones compatible with the heaviest elements?
- Are details standardised (formwork, reinforcement, connections), or is every element unique?
- Are interfaces between packages (civil, steel, equipment) drawn and assigned?
- Are the specified tolerances realistic for the intended methods?
- Has prefabrication been considered where it reduces time or risk?
- Are lead times for critical items built into the schedule?
- Are tests, inspections and hold points defined?
- Are HSE risks from methods (work at height, lifting, excavation) addressed in design?
- Is the baseline schedule based on checked quantities and production rates?
If several answers are uncertain, a targeted review of a few days before tender usually costs far less than the rework it prevents.