P6 schedule audit: 8 checks before accepting a baseline

A baseline schedule accepted without checking becomes the basis of all progress tracking and every claim. Eight simple checks help judge its quality before accepting it.

The eight checks

  1. Logic: every activity has at least one predecessor and one successor (except start and finish).
  2. Constraints: imposed dates are rare and justified.
  3. Lags: no negative lags; positive lags limited and explained.
  4. Relationship types: most links are finish-to-start.
  5. Durations: long activities are broken down so they can be tracked.
  6. Float: very high total float points to missing logic.
  7. Critical path: continuous from project start to finish.
  8. Resources and costs: loaded where the contract requires it.

Most of these checks can be automated from a schedule export; the interpretation remains an experienced planner's job.